DUE DILIGENCE & REUSE PLANNING

Banking Sunnyside Landfill

A proposal to accelerate redevelopment of the 240-acre former Holmes Road Landfill into a community asset through a land banking agreement with the Houston Land Bank.

THE OPPORTUNITY

Opened around 1937 in the historically Black Sunnyside neighborhood and capped by 1976, the 240-acre Sunnyside (Holmes Road) Landfill has long carried the community’s environmental burden.

In August 2025, the City of Houston engaged HLB to evaluate accelerating its redevelopment through a land banking agreement—building directly on HLB’s successful banking and cleanup of the Velasco Street Incinerator.

HLB proposes a Professional Services Agreement to deliver Phase I: Due Diligence & Reuse Planning.

ABOUT HLB

Public local government corporation, authorized by Texas SB 1679

In good standing with the U.S. EPA and TCEQ

$7M+ in EPA grant funding secured to date

Proven success on Velasco St. Incinerator & Hays St. (Yellow Cab) sites

HOW THE FUND SUPPORTS YOU
Technical Review

ASTM E2247-23 Phase I ESA satisfying CERCLA All Appropriate Inquiry for landowner liability protections.
→ Phase I ESA report

Highest & Best Use Analysis

Evaluate reuse options that are legally permissible, financially feasible, maximally productive, and community-supported.
→ Detailed report + summary presentation

Liability & Risk Assessment

Analysis of Brownfields Cleanup Alternatives (ABCA) with comparative cleanup costs and a project risk memo.
→ ABCA report + risk analysis memo

KEY DECISION POINT: Proceed to Reuse Planning or pass

Reuse Planning & Resource Roadmap

Predevelopment plan including financial modeling, milestones, funding roadmap, and community engagement strategy.
→ Reuse Plan + Resource Roadmap

Evaluation of Transfer

Draft terms and conditions to serve as the baseline for negotiating the Land Banking Agreement.
→ Draft term sheet

PHASE I AT A GLANCE
$410K

Total Phase I investment

6–9 months

Estimated duration

5

Tasks across 2 stages

240 acres

to be evaluated

KEY ASSUMPTIONS

Existing assessment data is sufficient; no new site or geotechnical work required

Legal fees and insurance purchases are excluded from Phase I

Community engagement begins in later stages

PHASE I SCHEDULE & COST ESTIMATE

TASK

DURATION

COST

FUNDING

STAGE 1 — DUE DILIGENCE

1 · Technical Review (Phase I ESA)

8 weeks

$30,000

EPA CWA

2 · Highest & Best Use Study

18 weeks

$50,000

KSU TAB

3 · Liability & Risk Assessment

12 weeks

$60,000

tbd

HLB Operations & Oversight

---

$60,000

tbd

STAGE 2 — REUSE PLANNING & TRANSFER (UPON ADMINISTRATION APPROVAL)

4 · Reuse Plan & Resource Roadmap

12 weeks

$70,000

TBD

5 · Evaluation of Transfer (draft terms)

12 weeks

$100,000

TBD

HLB Operations & Oversight

---

$40,000

tbd

Total Phase I

~6–9 months

$410,000

Mixed